Quarterly Roadmap (Indicative)¶
This is an indicative quarterly sequencing of the ecosystem phases for planning conversations. The authoritative timeline is the 2026 Roadmap; where they differ, the roadmap wins.
gantt
dateFormat YYYY-MM-DD
title Ecosystem Phases (Indicative)
section Foundation
Phase 0 Documentation :done, p0, 2026-01-01, 60d
section Core Platform
Phase 1 Core Foundation :active, p1, 2026-02-01, 150d
section Factory
Phase 2 Developer Factory :p2, after p1, 120d
section Horizontal
Phase 3 Horizontal SaaS :p3, after p2, 150d
section Verticals
Phase 4 First Verticals :p4, after p3, 180d
section Ecosystem
Phase 5 Marketplace :p5, after p4, 150d
Phase 6 Advanced AI Factory:p6, after p5, 180d
Hold "Alt" / "Option" to enable pan & zoom
Quarter View¶
| Quarter | Focus | Phases |
|---|---|---|
| Q1 | Documentation + core platform start | 0, 1 |
| Q2 | Core platform + factory | 1, 2 |
| Q3 | Factory + horizontals | 2, 3 |
| Q4 | Horizontals + first verticals | 3, 4 |
| Following year | Verticals, marketplace, advanced factory | 4, 5, 6 |